Philippines coal mine contract dispute threatens domestic energy supply
Uncertainty over the operating contract for the Philippines' biggest coal mine is putting pressure on a major domestic fuel source before the current agreement expires in July next year. The dispute is already curbing output and investment at Semirara Mining and Power Corp., while raising the prospect of higher import dependence and supply risks for the power grid.
Highlights
- Semirara Mining and Power Corp.'s coal output is projected to drop to over 13 million tons in 2024 from 19.9 million tons last year due to contract uncertainty and operational scale-backs.
- The bidding process for Semirara's coal mine contract, closing Dec. 11 with award expected in January, faces criticism over requiring surrender of over 55 billion pesos in assets.
- Semirara's contract dispute threatens domestic energy supply as its mine fills nearly all local coal demand and supplies about 20% of Philippine total energy, while shares fell over 63% year-to-date.
Bidding terms and operational slowdown
As reported by Bloomberg, citing BusinessWorld Online, the government is moving ahead with a bidding process for the next operator of Semirara Mining and Power Corp.'s coal mine, with proposals due on Dec. 11 and the award and contract signing scheduled for early January. The Department of Energy published terms last week that say bids will be evaluated based on the government's share in the coal business after several months of delay.Semirara has criticized the process as unfair, arguing that bidders are being required to surrender more than 55 billion pesos in assets already recovered or depreciated under the current contract. The company has asked a court to intervene, while the Department of Energy did not respond to requests for comment in the source report.
Operations on Semirara Island are already being scaled back as the contract deadline approaches. More than 200 dump trucks, bulldozers and excavators are idle, one site has shut because of seawater seepage, and about 40% of the mine's 4,000 employees have been retrenched in recent months.
Chairman and Chief Executive Officer Isidro Consunji said output is projected to fall to more than 13 million tons this year from a record 19.9 million tons last year as the company curtails activity eight months before the contract ends. He also said the company is holding back capital spending because it cannot justify buying equipment to raise capacity while control of the mine remains uncertain.
Energy market and regional implications
Semirara's mine produces nearly all of the Philippines' locally mined coal and supplies about one-fifth of the country's total energy demand, making the contract dispute significant for the wider power market. Coal still generates almost 60% of Philippine grid electricity, despite the country's push toward cleaner energy sources.The risk comes as the Philippines already faces some of Southeast Asia's highest energy prices and remains exposed to imported fuel costs. Any disruption to the handover could force greater reliance on coal imports from Indonesia, the country's main external supplier, at a time when supply security remains a concern.
Jasper Timoteo Ondap, an analyst at Regina Capital and Development Corp., said a disorderly transition could trigger disputes over the handover, litigation and the loss of operating know-how, hurting production and efficiency. Political scrutiny is also increasing, with House member Mark Cojuangco warning last week that the country could face a severe disruption in domestic coal supply by July next year.
Several interested local groups have visited the property since the bidding opened, including San Miguel Corp. Chairman and Chief Executive Officer Ramon Ang said the conglomerate generally joins public tenders when asked whether it would bid. Meanwhile, Semirara's shares have fallen more than 63% this year, making them the worst performer on the Philippine Stock Exchange Index amid uncertainty over the contract.
The latest update follows our earlier article on Peak Energy renewables expansion as fuel-supply disruptions boosted clean-power interest in the Philippines.