Activity is picking up around one of the few onshore gas projects in Western Australia that can potentially feed export markets. Black Mountain Energy says it has lined up major U.S. oilfield service providers for Project Valhalla in the Kimberley region, even as the development still awaits key approvals and faces sustained environmental opposition.
Highlights
- Black Mountain Energy contracts Halliburton, SLB, Liberty Energy, and Helmerich & Payne for fracking services at Project Valhalla in Western Australia's Kimberley region.
- Project Valhalla faces more than 8,000 environmental appeals and may not drill its first well until late decade due to ongoing regulatory and stakeholder challenges.
- Valhalla and Mitsui's Waitsia are the only two Western Australia onshore gas projects with exemptions to supply liquefied natural gas, bypassing the state's domestic-only export restrictions.
Contractor lineup for Project Valhalla
As reported by Reuters, citing Black Mountain Energy in a statement on Wednesday, the company has hired Halliburton, SLB, Liberty Energy and drilling rig provider Helmerich & Payne to provide fracking-related services for its Project Valhalla in Western Australia's Kimberley region.Liberty Energy was founded by U.S. Energy Secretary Chris Wright. Some of the same service groups also operate in Australia's Beetaloo Basin in the Northern Territory, while a Helmerich & Payne rig is also drilling in Queensland's Taroom Trough.
Black Mountain Energy listed on the Australian Securities Exchange at the end of 2021 but left less than three years later, with its share price at a fraction of its listing level. The company is now awaiting state and environmental approvals for a multiwell campaign.
Approval hurdles and state gas policy
Environmental activists have opposed the fracking plan for years and have filed more than 8,000 appeals against the project's provisional recommendation from the state's Environmental Protection Authority. Company filings with environmental regulators indicate Valhalla could drill up to 20 wells over several stages, but the first well has been delayed several times and may not start until near the end of the decade.If approvals are granted, the company must still negotiate with local stakeholders, including indigenous groups. Executive director and chief operating officer Michael Laurent says in the statement that, while key project approval outcomes are not yet determined, the company is becoming more confident that facts and science will allow it to progress an appraisal program.
Western Australia lifted its fracking moratorium in late 2018 but permits the practice in only 2% of the state. Valhalla is one of only two onshore gas projects in Western Australia with an exemption allowing gas to be sent to liquefied natural gas projects rather than being limited to domestic supply; the other is Mitsui's Waitsia project, which has a contract with BP to supply the Woodside Energy-operated North West Shelf. Separately, the state government says on Wednesday that it has secured a carve-out from the federal gas reservation scheme because Western Australia already operates its own domestic gas reservation policy.
As highlighted earlier, Vantris Energy launched a strategic review of its Brazilian joint venture as it weighs third-party interest.