Philippine Ports Authority awards Zamboanga terminal contract for P577.81 million
The Port of Zamboanga's passenger terminal project is moving forward again after years of delays tied to design, location and pandemic-related challenges. The new award marks a key step in the port's modernization, which the regulator views as important for regional trade and economic growth.
Highlights
- Philippine Ports Authority awarded a P577.81 million Port of Zamboanga passenger terminal contract to NBCDC Corp. on Nov. 25 after rebidding.
- The original contract was terminated in 2025 due to design misalignment, delays, and location-specific challenges, prompting an October rebid with two participants.
- Modernization of the Port of Zamboanga via this project is underlined as critical for regional trade and broader economic growth beyond passenger capacity.
Contract award and project timeline
As reported by BusinessWorld Online, the Philippine Ports Authority awarded the contract for the construction of the passenger terminal at the Port of Zamboanga to Bataan-based NBCDC Corp. in a notice of award dated Nov. 25.The contract is valued at P577.81 million. The port regulator had reopened the bidding in October after the project, first awarded to MAC Builders, Inc. on Jan. 21, 2021, was terminated in 2025 because of operational concerns that included design misalignment and prolonged delays.
The Philippine Ports Authority has also said location-specific challenges, design considerations and the pandemic contributed to the setbacks that delayed the terminal project.
Regional trade significance and bid outcome
According to the Philippine Ports Authority Bids and Awards Committee, only two companies joined the latest bidding process, with MAC Builders as the other participant.NBCDC was declared the lowest calculated and responsive bidder, and the committee said post-qualification procedures validated the company's eligibility and its technical and financial submissions. Based on the Philippine Contractors Accreditation Board's portal, NBCDC undertakes roads, highways, pavements, railways, ports, harbors and offshore engineering projects.
The modernization of the Port of Zamboanga is considered critical for regional trade and broader economic growth in the area, underscoring the project's importance beyond passenger facilities alone.