Philippines infrastructure flagship delays raise cost and delivery risks

Philippines infrastructure flagship delays raise cost and delivery risks
Rising risks for major projects

The Philippines is facing mounting execution pressure on major infrastructure works scheduled for completion by 2028, with most projects already running behind plan. The delays affect 33 of 37 projects worth a combined P1.45 trillion as of September, increasing the risk of higher costs and weaker economic returns.

Highlights

  • All six flagship infrastructure projects targeted for 2026 completion are behind schedule, as well as nine of 12 for 2027 and 18 of 19 for 2028.
  • Significant delays on high-profile projects slated for 2028 include the P735.63-billion New Manila International Airport, P77-billion MRT-7, and P70.81-billion Davao City Bypass.
  • DEPDev cites site-related issues affecting 21 of 201 projects and P44.5 billion allocated in the 2027 national budget for 18 priority projects due by 2028.

Project slippages and funding pressure

As reported by BusinessWorld Online, the Department of Economy, Planning, and Development is warning that delays in infrastructure flagship projects could erode their benefits and make them more expensive to finish, as agencies seek cost adjustments to reflect price changes.

DEPDev Secretary Arsenio M. Balisacan says the government is very concerned about the pace of implementation and is focusing on closer project monitoring and the availability of funding. He says delays mean the country gives up benefits that the projects could have delivered earlier, while the value of those benefits declines when pushed further into the future.

Data from DEPDev show that all six projects targeted for completion in 2026 are behind schedule, along with nine of 12 due in 2027 and 18 of 19 due in 2028. Among the delayed projects due in 2028 are the P735.63-billion New Manila International Airport, the P77-billion Metro Rail Transit Line 7 Project, the P70.81-billion Davao City Bypass Construction Project and the P28.78-billion Cebu Bus Rapid Transit Project.

Portfolio issues and budget alignment

Of the 37 projects targeted for completion by 2028, seven report site-related issues, including right-of-way constraints, while three face procurement problems and two have budget and funds flow concerns. Across the government’s full infrastructure flagship portfolio of 201 projects with an indicative cost of P10.25 trillion, site issues are the most common implementation problem, affecting 21 projects.

DEPDev data show the number of projects targeted for completion by 2028 falls to 37 in the third quarter of 2026 from 60 in the second quarter of 2025, reflecting completed works, revised schedules and changes in the project list. Nineteen projects are rescheduled for completion beyond 2028, while eight projects are completed from 2023 to 2025 and 156 are targeted for completion after 2028.

To address the slippages, DEPDev identifies better alignment between budget programming and project completion schedules as a key step, with priority for projects in advanced stages of readiness and with confirmed delivery timelines. The agency also calls for updated action plans for delayed projects, clear milestones and accountability, and stronger coordination to resolve right-of-way and permitting bottlenecks; under the proposed 2027 national budget, P44.5 billion is allocated to 18 flagship projects targeted for completion by 2028.

We have also analyzed Philippines stagflation risks, highlighting how budget discipline and governance constraints can squeeze growth.