Tasmania lawmaker pushes data centre moratorium after disclosing Goodman stake
Tasmania's parliament is set to debate a proposed pause on new data centre developments as pressure grows for stricter planning and resource rules. The bill comes as independent MP Peter George has declared shares in Goodman Group, whose development pipeline is heavily weighted toward data centres.
Highlights
- Franklin independent Peter George disclosed a Goodman Group stake before tabling his bill for a moratorium on new Tasmanian data centres.
- Goodman reported over $15 billion of its $19.7 billion global work in progress tied to data centre development, with its pipeline share rising to 78% by September.
- Tasmania's new data centre expectations document lacks binding rules, drawing criticism from Labor, Greens, and George, all supporting a project moratorium until stricter requirements are set.
Disclosure and moratorium proposal
As reported by ABC News, Franklin independent Peter George has listed Sydney-headquartered Goodman Group among the interests held in his retirement plan before parliament considers his bill for a moratorium on new data centres.The company was not included in his disclosure 12 months earlier, when he listed shares in Rio Tinto and Endeavour Group, both of which he later divested as being inconsistent with his values. In its full-year results released in August, Goodman said data centre development accounted for more than $15 billion of its $19.7 billion global work in progress, with the share of its pipeline rising from 57 per cent to 68 per cent by September last year and now to 78 per cent.
George has argued that Tasmania lacks specific planning controls and a broader framework for data centre development, citing uncertainty around costs and benefits and what he describes as growing community resistance globally. He says his bill would pause new projects until questions around location, energy use and water consumption are addressed, while requiring data centres to be confined to designated zones with public consultation and appeal rights preserved.
George says his interest in Goodman reflects its broader commercial holdings and that he will review the investment as the company's portfolio changes. He says this shows he is technologically neutral and that data centres should be built only in suitable locations and under appropriate conditions, not in residential areas, light commercial zones or on prime agricultural land.
Political pressure on Tasmania's data centre rules
The debate comes after the Tasmanian government last week released an expectations document for data centre developments, setting out that projects should partner with new renewable energy developments, use water efficiently and contribute to a community benefit fund. The guidance says developers would not be expected to procure or build new firming capacity if that capacity is already available from Hydro Tasmania.Labor and the Greens criticised the document for stopping short of binding rules before developments proceed, and both backed a pause on new projects until stronger requirements are in place. George has supported a moratorium for months and says a more cautious approach is needed to protect the state's natural heritage, power supplies, carbon-neutral ambitions and residential amenity.
Labor leader Josh Willie told parliament on Tuesday that the government had given developers too much flexibility, arguing protections on power, water and community benefits were left to private negotiation. Premier Jeremy Rockliff defended the expectations, saying Tasmania needs to strike the right balance and that developers unwilling to comply should take their investment elsewhere.
Goodman recently withdrew its proposed A$1.2 billion Project Mars facility on Sydney's north shore after community opposition and regulatory changes. The company has no publicly announced proposals for Tasmania.
In a previous article, we explained Compass Datacenters securitization involving a Fitch-expected AAA rating on a $275 million note.