Malaysia urges data center electricity tariffs to reflect coal costs

Malaysia urges data center electricity tariffs to reflect coal costs
Data center tariff under review

A new proposal on data center electricity tariffs has emerged as Malaysia considers ways to protect households from rising energy costs. Yeo Bee Yin said new large consumers should pay rates that more accurately reflect their supply costs, while households continue to benefit from cheaper electricity.

Highlights

  • Former energy minister Yeo Bee Yin urges the government to immediately exclude coal costs from the base electricity tariff for data centers, without waiting for the 2029–2030 wholesale market.
  • The government increased connected load charges and introduced an ultra-high-voltage tariff effective 1 July 2025 to limit excessive capacity bookings by data centers.
  • The Energy Commission projects Peninsular Malaysia's electricity reserve margin will remain at 24%–27% from 2027 to 2035; the 2025 margin was estimated at 25%.

This article was translated from the original. Read the original version by our correspondent here.

Proposed tariff review for large consumers

As reported by The Edge Malaysia, former energy minister Yeo Bee Yin on Wednesday urged the government to exclude coal-fired generation from the calculation of the base tariff for data centers and implement the measure immediately, rather than wait for a separate wholesale electricity market for large consumers, which is only expected to be introduced several years from now.

The Puchong MP said electricity prices for data centers need to be set correctly now, not just in 2029 and 2030. She said this approach would help keep household electricity costs at manageable levels while allowing prospective investors to assess whether their business models remain viable when actual supply costs are taken into account.

Yeo also warned that building new power plants to meet uncertain demand could leave other consumers bearing the costs in the future if market conditions or technology change and the expected demand fails to materialize. She said data centers can be built within 12 to 24 months, whereas gas-fired power plants now take four to seven years, taking supply chain constraints into account.

Implications for households and the energy system

As a temporary measure before new generation capacity becomes available, Yeo urged the government to step up efforts to encourage large consumers, including factories, to reduce electricity demand during peak hours. She also proposed extending tax incentives to companies that lease battery energy storage systems so factories can install storage facilities without significant upfront expenditure.

Deputy Prime Minister Datuk Seri Fadillah Yusof, who is also the Minister for Energy Transition and Water Transformation, hinted in mid-October that a "user-pays" pricing approach was being considered to protect households from rising electricity costs. However, details on rates, consumption thresholds, and the implementation timeline have yet to be announced.

His deputy, Datuk Seri Abdul Rahman Mohamad, said on Wednesday that Peninsular Malaysia's electricity reserve margin is projected to be 24% to 27% from 2027 to 2035. According to the Energy Commission, the country's reserve margin stood at 25% in 2025. For now, the government has increased connected load charges to curb excessive capacity bookings by data centers and introduced an ultra-high-voltage tariff structure, effective 1 July 2025.

As a reminder, we previously reported on local content targets for new data centers approved under the DCTF.