Bangladesh's Rooppur plant begins second trial power supply to grid
Bangladesh is advancing testing at its first nuclear power facility as the Rooppur Nuclear Power Plant starts a second trial electricity supply to the national grid on 23 November 2026. The latest phase is set to deliver around 300MW to 350MW for 10 to 24 hours while engineers carry out technical checks on generation systems and grid operations.
Highlights
- Rooppur plant began its second trial power supply to the grid at 10:20am on 23 November 2026 as part of commissioning tests.
- The first trial on 17 November 2026 delivered about 375MW for eight and a half hours, valued at approximately Tk 2 crore.
- Full commercial operation, with a projected capacity of 1,150MW, is targeted between February and March 2027 pending further safety tests and approvals.
Testing phase and generation timeline
The Business Standard reported that the second trial supply began at 10:20am on 23 November 2026 as part of the plant's ongoing commissioning process. The electricity sent to the grid during this stage is being used to support technical tests on the power generation system and its interaction with the national network.This follows the first trial supply on 17 November 2026, when the plant initially delivered about 375MW for roughly eight and a half hours. The estimated market value of that earlier electricity supply was about Tk 2 crore.
Project Director Dr. Md Kabir Hossain said the second trial grid connection marks an important step in the testing process. He said the facility is expected to gradually raise output as commissioning continues.
Expected role in Bangladesh's power supply
The plant aims to reach full operational capability by February to March 2027, with potential generation of about 1,150MW. That capacity is expected to help ease electricity shortages during the summer period.The current supply to the grid does not yet amount to full commercial operation. Further safety tests and regulatory approvals are still required before the plant can enter regular service.
As highlighted earlier, Rohas Tecnic contract covered a turnkey 132kV transmission line project awarded by Power Grid Bangladesh.