LAX SkyLink delays deepen cost overruns in airport modernization plan
Los Angeles is still waiting for a direct rail link at LAX even as the airport pushes ahead with a broader $30 billion modernization effort. The automated SkyLink people mover, designed to ease chronic traffic congestion, is now nearly $1 billion over budget and its opening has slipped to 2027 from an original 2023 target.
Highlights
- LAX SkyLink project's total costs have risen to nearly $3 billion after a settlement added $550 million to the original $1.9 billion contract.
- Final testing has exceeded 200 days, delaying project completion and jeopardizing readiness for the Super Bowl in February and the 2028 Olympics.
- Fitch Ratings downgraded the project's debt to B- in September amid operational, contractual, and financial risks, with no confirmed opening date as of now.
Contract disputes and testing setbacks
As reported by The Guardian, the less than 2.5-mile SkyLink project broke ground in 2019 under then mayor Eric Garcetti and is intended to connect LAX terminals with a ride-share area, a transit center and a car rental hub. Officials say the system is 99% complete, but the final testing phase, which requires at least 30 consecutive days of uninterrupted operation, has now stretched beyond 200 days.The project is being overseen by Los Angeles World Airports, which hired LAX Integrated Express Solutions, or Linxs, under a public-private partnership to design, build, operate and maintain the system for 30 years. That arrangement was presented as a cost-effective model, but disputes over design codes and a large volume of change orders led to a settlement that added $550 million to the original $1.9 billion contract value, with total costs rising to nearly $3 billion.
A Los Angeles county civil grand jury said last year that weaknesses in the contract allowed Linxs to press hundreds of change orders and exploit slow city responses, contributing to major delays and extra payments. In July, Linxs sued the city over alleged contract breaches, including faulty electrical equipment and delays tied to a solar energy agreement, while airport officials said the claims are false and argued the main problem is Linxs' failure to complete required testing safely and reliably.
Pressure builds ahead of major events
The delays are increasing pressure on Los Angeles as city leaders try to show progress in a wider transit buildout and prepare for global sporting events. The airport rail link was expected to improve access for millions of travelers, but it missed the World Cup period, faces doubts over readiness for the Super Bowl in February and remains under scrutiny with the 2028 Olympics approaching.The separate 11-acre LAX/Metro Transit Center, which the people mover is meant to serve, opened in June 2025 after construction started more than two years after SkyLink. That contrast has sharpened criticism from local transit advocates, who say the airport link has shifted from a showcase infrastructure project into a costly operational and financial risk.
Fitch Ratings downgraded the project's debt to B- in September, just above a level considered substantial credit risk. Under settlement terms tied to the additional $550 million payment, Linxs must deliver a passenger-ready system by 8 December this year, but airport officials say no opening date can be confirmed until final testing is completed.