Global power grids face investment push as UN targets 80mn km expansion by 2040
Power transmission is moving to the centre of the energy transition as policymakers confront mounting delays, rising costs and weak capacity across electricity networks. The pressure is especially acute in fast-growing and underserved regions, where grid bottlenecks are slowing renewable deployment and limiting access to power.
Highlights
- The United Nations launches the Global Grids Accelerator aiming to mobilize investment for 80mn km of new or refurbished power lines by 2040, focusing initially on Africa and south-east Asia.
- Grid connection queues reached 1,700 GW for renewable projects and 600 GW for battery storage in 2023, while permitting delays, technical hurdles, and supply chain inflation hamper progress.
- Annual global grid infrastructure spending rises from $300bn in 2020 to $400bn in 2025, but must increase another 50% by 2030 to meet demand, with the U.S. announcing a $1.9bn package for 31 projects.
UN plan targets transmission build-out
As reported by Financial Times, citing the United Nations, secretary-general António Guterres this week launches the Global Grids Accelerator to mobilise investment in transmission and distribution networks, with an initial focus on Africa and south-east Asia. The initiative is designed to bring together governments, investors and technical experts, while stopping short of creating a new financing institution.The programme reflects a broader shift in energy policy from headline renewable capacity targets to the practical challenge of moving electricity across systems that are not expanding fast enough. Guterres says grids are the "arteries of the energy transition", and the UN is pushing for 80mn kilometres of power lines to be added or refurbished by 2040 to support clean energy goals.
Grid constraints are already weighing on new projects. According to the International Energy Agency, renewable projects with 1,700 gigawatts of capacity and a further 600 gigawatts of battery storage were stuck in grid connection queues last year, while some connected wind and solar projects are still being curtailed because transmission capacity is inadequate.
Costs, delays and regional pressure points
Developers and grid operators are facing a mix of long permitting timelines, technical complexity and supply chain inflation. The International Energy Agency says new grid projects often take more than a decade to complete, while equipment such as transformers has become markedly more expensive over the past five years as demand runs into manufacturing constraints.Annual investment in grid infrastructure rises from about $300bn in 2020 to about $400bn in 2025, but the International Energy Agency says spending still needs to increase by another 50 per cent by 2030 to meet projected global electricity demand. That funding gap is becoming more visible in Europe, where high power prices are feeding competitiveness concerns, and in the U.S., where operators are struggling to keep up with rising electricity demand from data centres supporting AI.
The challenge is sharper in developing economies, particularly in Africa, where more than 500mn people still lack access to electricity and where future energy demand growth is expected to be strongest. In the U.S., the Trump administration on the previous day announces a $1.9bn federal package for 31 grid projects, underlining how network investment is becoming a central issue for both climate policy and industrial growth.
In our earlier article on Europe’s energy price crunch heading into winter, we covered the European Commission’s warning that tens of millions of people could face severe affordability pressure without additional government support. We also noted that officials were weighing emergency measures and regulatory flexibility, while trying to keep any short-term relief consistent with the EU’s longer-term shift away from imported fossil fuels.