BWXT Canada to build first transportable nuclear power plant for New Brunswick pilot

BWXT Canada to build first transportable nuclear power plant for New Brunswick pilot
Canada’s first portable reactor

Ontario and New Brunswick are advancing a microreactor project aimed at expanding domestic nuclear supply chains and power options for remote communities. The planned 50-megawatt facility in Belledune is set up as an Indigenous-led pilot that officials say will support jobs, training and future deployment of transportable reactors across Canada.

Highlights

  • BWXT Canada will fabricate and deploy Canada's first Transportable Nuclear Power Plant using BWXT Advanced Nuclear Reactor technology for a 50 MW pilot in Belledune, New Brunswick.
  • The Belledune project, developed by Prodigy Clean Energy, is expected to create over 150 jobs during development and 40 long-term positions, supporting up to 40,000 homes.
  • Ontario positions itself as a nuclear manufacturing hub, with its sector supporting 80,000 jobs and the broader buildout projected to create 150,000 jobs and add C$800 billion to the economy.

Belledune project and supply chain role

According to Ontario Newsroom, Ontario-based BWXT Canada has been selected to fabricate and deploy Canada’s first Transportable Nuclear Power Plant using BWXT Advanced Nuclear Reactor technology for the Indigenous-led project in Belledune, New Brunswick.

The project is developed by Prodigy Clean Energy and is designed to deliver 50 megawatts of baseload electricity, enough to power up to 40,000 homes. Officials say the development phase is expected to create more than 150 jobs, with about 40 long-term positions once the facility is operational.

Transportable nuclear plants are designed to be built off site and moved to where electricity is needed, a model intended to broaden access to clean power for remote and northern communities, Indigenous communities, industrial users and grid-connected locations. Under an agreement with Pabineau First Nation and Eel River Bar First Nation, the Belledune pilot is also planned to include a First Nations-owned commercial power generation facility, an energy innovation campus, operations and maintenance functions, workforce training and an Indigenous Energy Innovation Visitor Centre.

Economic and industry implications for Canada

For Ontario, the selection reinforces the province’s role in Canada’s nuclear manufacturing base as governments push to localize critical energy supply chains and reduce exposure to U.S. tariffs. The province says its nuclear sector already supports 80,000 jobs across more than 200 companies, with more than 90 per cent of project costs remaining in Canada.

Ontario is linking the Belledune announcement to its broader Energy for Generations strategy, which includes refurbishment work at Darlington and Pickering and development of the G7’s first grid-scale small modular reactor. The province says its wider nuclear buildout is expected to create 150,000 jobs and contribute C$800 billion to the Canadian economy, while expanding reliable and affordable power capacity for homes, industry and investment.

In our earlier article on Ontario’s $38 million funding to add 1,504 new seats at Trent University, we covered the province’s push to expand postsecondary capacity in high-demand fields such as STEM, health, trades and education. We noted that the Trent expansion is part of a wider plan to build a stronger talent pipeline and support economic growth and competitiveness amid tariff-related uncertainty.

This material may contain third-party opinions, none of the data and information on this webpage constitutes investment advice according to our Disclaimer. While we adhere to strict Editorial Integrity, this post may contain references to products from our partners.