Hunterston B awards Costain decommissioning pipeline contract in Scotland
Hunterston B is advancing its decommissioning programme with a new infrastructure contract at the North Ayrshire site. The award to Costain is worth more than £7 million and is the first major contract since the station transferred to Nuclear Restoration Services in April 2026.
Highlights
- Costain secured a contract to design, build, and install a new effluent discharge pipeline at Hunterston B, with project completion expected in 2028.
- The pipeline allows permanent shutdown of the older system, enabling over £3 million in annual savings on power, operational, and maintenance costs.
- The project, funded by the Nuclear Liabilities Fund, demonstrates ongoing investment in UK nuclear decommissioning infrastructure and extends Costain's partnership with Nuclear Restoration Services.
Pipeline project and delivery timeline
As reported by GOV.UK, Costain has been appointed to design, build and install a new active effluent discharge line that will allow Hunterston B to continue controlled discharges while an older generation-era system is shut down.The new discharge line is intended to support the site through its decommissioning phase, when smaller volumes of effluent still need to be treated and discharged to sea as projects continue. The pipeline is expected to be completed in 2028 and will be installed within an existing culvert, allowing operations to continue under the site's environmental permits.
Andy Dalling, Hunterston B Site Director, says the project is an important step in the site's decommissioning journey. He says the replacement line will allow the permanent shutdown of a system built for electricity generation, cutting more than £3 million a year in power, operational and maintenance costs.
Regulatory compliance and wider sector impact
Effluent discharges from the site remain subject to legal requirements, regulatory limits and environmental standards set by the Scottish Environment Protection Agency. Hunterston B says all discharges are carefully controlled as the site moves further away from its power generation and defueling phases.Costain says the contract extends its partnership with Nuclear Restoration Services as Hunterston B enters the next phase of its lifecycle. Bob Anstey, Sector Director for Defence and Nuclear Energy at Costain, says the work will support compliant operations and be delivered to high safety, quality and environmental standards.
Decommissioning at Hunterston B is funded by the Nuclear Liabilities Fund, which is set up to cover costs linked to this phase of work at the Scottish plant and seven other UK nuclear power stations. The contract signals continued investment in specialist infrastructure needed to reduce operating costs and manage long-term nuclear cleanup obligations.