NDA group site transfer programme wins national project award in UK nuclear decommissioning

NDA group site transfer programme wins national project award in UK nuclear decommissioning
NDA wins major site award

After the first two Advanced Gas-cooled Reactor sites moved from EDF to the Nuclear Decommissioning Authority group earlier this year, the transfer programme is gaining recognition for a complex handover in the UK nuclear sector. The award highlights a model that combines workforce transfer, operational change and long-term decommissioning plans across seven sites.

Highlights

  • EDF and the Nuclear Decommissioning Authority (NDA) group's Nuclear Restoration Services won Programme of the Year at the 2026 Association for Project Management Awards for the first AGR nuclear site transfer.
  • The transfer of Hunterston B and Hinkley Point B marks the first two of seven AGR sites shifting from EDF to NDA group, with five more sites planned for transfer over the next decade.
  • Around 500 staff moved from EDF to NRS as part of the site handovers, accompanied by IT, regulatory, and funding changes funded by the Nuclear Liabilities Fund.

Award follows first AGR transfers

As reported by GOV.UK, the team behind the first transfer of an AGR nuclear site from EDF to the NDA group has won Programme of the Year at the Association for Project Management Awards 2026. The Nuclear Restoration Services and EDF Transition and Transfer Programme was also a finalist in the Innovation in Project Management category.

The judges praised the programme's joint governance, collaborative culture and ability to align hundreds of stakeholders around a shared objective. The recognition follows the transfer of Hunterston B in North Ayrshire and Hinkley Point B in Somerset, the first two of seven AGR sites due to move from EDF ownership to the NDA group.

With electricity generation and defueling completed at both sites, NRS is now the site licensee responsible for decommissioning. Five further site transfers are due to follow over the next decade.

Workforce transition and sector implications

Moving a nuclear power station, its workforce and associated responsibilities to another company is a multi-year process involving operational, regulatory and funding changes. Around 500 staff transferred from EDF to NRS, alongside changes to IT systems and contractual and funding arrangements.

Sohail Ashraf, AGR Transfer Programme Director at NRS, says the result reflects collaboration across teams and underlines a continued commitment to future employment and support for local communities during decommissioning. Clare Sharpe, EDF Nuclear Decommissioning Director, describes the handover as highly complex and says the programme depended on sustained teamwork across the organisations.

The AGR transfers are significant for the NDA because they mark its first major new mission since it was established. The work is funded by the Nuclear Liabilities Fund, linking the programme to the long-term management of the UK's civil nuclear legacy.