Berjaya Construction takes on construction and design work for Sanglang Port project in Perlis
The development of Sanglang Port in Perlis is moving into the implementation phase, with Berjaya Construction Bhd appointed to carry out the design and construction work for the port infrastructure. The phased maritime project is estimated to have a total development cost of around RM1.2 billion and aims to strengthen logistics links and make the state more attractive to investors.
Highlights
- Berjaya Construction Bhd has taken on procurement, design development and construction work for the Sanglang Port project, with total development costs estimated at RM1.2 billion.
- The project is divided into two main phases: the first includes a 2–4 km offshore bridge and terminal (30 months), while the second covers LPG facilities (12 months).
- Berjaya Property Bhd shares remained at 25 sen, with a market capitalisation of RM1.25 billion, while the project is expected to boost Perlis's investment appeal and logistics infrastructure.
This article was translated from the original. Read the original version by our correspondent here.
Port development scope and schedule
As reported by The Edge Malaysia, citing its Bursa filing, Berjaya Construction Bhd will work with Sanglang Port Mutiara Perlis Sdn Bhd, the port's owner and developer, to carry out procurement, design development, engineering and construction delivery for the Sanglang Port project in Perlis.The filing did not disclose the specific value of the contract to be undertaken by Berjaya Construction. However, the project's total development cost is estimated at around RM1.2 billion, including preliminary construction costs estimated at RM675 million. Development will be carried out in phases, subject to relevant approvals, implementation arrangements and construction milestones.
The first phase, which includes a 2 to 4-kilometre offshore bridge and associated terminal, is estimated to take 30 months. The second phase, which includes liquefied petroleum gas landing facilities, is estimated to take 12 months.
Logistics impact and investment appeal in Perlis
The maritime infrastructure development aims to improve Perlis's maritime connectivity and complement newly completed logistics infrastructure, including the Tuanku Syed Sirajuddin Free Trade Zone, Perlis Inland Port and Chuping Valley Industrial Area.The project's master plan includes two multi-user terminals, a roll-on/roll-off terminal and a general cargo terminal along a 4-kilometre offshore bridge with a water depth of up to 11.9 metres. It also provides for five key maritime activities, including RORO operations, fishing facilities, general cargo handling, an energy hub and multi-user facilities.
In a statement on Wednesday, Berjaya Corporation Bhd founder Tan Sri Vincent Tan Chee Yioun said the project underscored the importance of investing in strategic infrastructure to support Malaysia's long-term economic growth and strengthen regional connectivity. Mutiara Perlis group founder and executive chairman Datuk Shabaruddin Ibrahim said improved cargo-handling capabilities and access to wider markets through Perlis Inland Port and Sanglang Port could make the state more attractive to investors in logistics, manufacturing, energy and related industries.
Berjaya Property Bhd shares were unchanged at 25 sen at midday on Wednesday, giving the company a market capitalisation of around RM1.25 billion.
In our previous coverage of Malaysia's market resilience and foreign investment inflows, we highlighted how the stability of local stocks amid global uncertainty continues to attract investor interest. The article also explained that the technology and financial sectors are expected to be key drivers of fund inflows, supported by investment in digital infrastructure and innovation, further strengthening the country's long-term growth outlook.