Mestron secures Seda approval to expand biogas plant capacity in Kelantan
Mestron Holdings Bhd is expanding its renewable energy generation plans in Gua Musang after receiving new approval to increase the biogas plant’s electricity export capacity. The move also sets higher feed-in tariff rates under a 21-year electricity sales framework, effective from 17 August 2029.
Highlights
- Mestron, through Liziz Biogas Sdn Bhd, has secured Seda Malaysia approval to increase net electricity export capacity to 2.36 megawatts (+18%) and installed capacity to 3.12 megawatts (+13%) at its Gua Musang biogas plant.
- The new FiA raises the feed-in tariff to 45 sen/kWh for the first 10 years and 43 sen/kWh for the next 11 years, starting 17 August 2029.
- Once the expansion is complete, the facility is expected to generate RM7.5 million in total annual revenue, subject to generation performance, under a 21-year renewable electricity sales framework.
This article was translated from the original. Read the original version by our correspondent here.
Approval details and upgrade plans
As reported by The Edge Malaysia, citing a Bursa Malaysia filing, the new feed-in approval from the Sustainable Energy Development Authority Malaysia, or Seda Malaysia, was granted to Mestron’s wholly owned indirect subsidiary, Liziz Biogas Sdn Bhd, to expand the facility in Gua Musang, Kelantan.The approval allows the group to increase the plant’s approved net electricity export capacity by 18% to 2.36 megawatts, from 2.00 megawatts previously. Approved installed capacity will rise 13% to 3.12 megawatts, from 2.76 megawatts previously.
Under the new FiA, the plant’s feed-in tariff will increase from 39.75 sen per kilowatt-hour to 45 sen per kilowatt-hour for the first 10 years, followed by 43 sen per kilowatt-hour for the next 11 years. Mestron also plans to acquire and install an additional 1.5-megawatt gas engine generator to increase the plant’s generation output and operational efficiency.
Revenue projections and implications for the renewable energy sector
Mestron estimates that the facility could generate approximately RM7.5 million in total annual revenue once the expansion is complete and the plant is fully commissioned, subject to actual generation performance, plant availability and operating conditions. The tariff is scheduled to take effect on 17 August 2029, establishing a 21-year framework for renewable electricity sales, subject to the relevant approval conditions.Mestron’s Gua Musang biogas plant began supplying renewable electricity to Tenaga Nasional Bhd in March 2023. The facility treats and captures methane-rich biogas produced from palm oil mill effluent, converting agricultural processing waste into clean electricity for the national grid while reducing greenhouse gas emissions that would otherwise be released through the open decomposition of waste.
In our previous coverage of MIDA’s efforts to connect 25 local companies with TNB Genco and TNB Renewables, we highlighted how the business-matching event at IGEM 2026 aims to strengthen domestic industry participation in the renewable energy supply chain. The initiative is positioned as a way to develop local specialist capabilities across engineering, construction, operations and services, while increasing domestic economic value as TNB’s green energy portfolio grows.