Philippines public works agency faces audit flags over delayed projects and low fund use
The Philippines' public works department comes under renewed scrutiny after state auditors identified broad implementation weaknesses across thousands of infrastructure and consultancy projects in 2025. The findings cover delayed execution, poor disbursement, missed construction targets and unresolved audit issues that together affect hundreds of billions of pesos in public spending.
Highlights
- Department of Public Works and Highways inefficiently implements 9,061 projects worth P531.79 billion in 2025 with over half of obligated funds undisbursed.
- Commission on Audit flags 50 multi-phase civil works contracts worth P4.62 billion as idle or partially operational, with P4.09 billion in unrecovered advances and technical defects identified in 1,172 projects.
- State auditors issue a qualified opinion on 2025 financial statements, citing P17.28 billion in uncorrected misstatements and total unsettled audit findings reaching P118.09 billion.
2025 audit findings on project delivery and spending
As reported by BusinessWorld, citing the Commission on Audit, the Department of Public Works and Highways inefficiently implements 9,061 infrastructure and consultancy projects worth P531.79 billion in 2025, with delays, prolonged suspensions and idle works slowing delivery. State auditors say deficiencies in project planning, detailed engineering, contract administration, supervision, monitoring and the timely resolution of implementation issues contribute to the weak execution. The audit also shows the agency fails to disburse more than half of its obligated funds. Of the P1.077 trillion obligated from a P1.357-trillion budget allocation, only P491.72 billion, or 45.65%, is disbursed by the end of 2025, leaving P585.47 billion undisbursed. Another P33.67 billion in cash allocations is unused and reverts to the Bureau of the Treasury because of procurement delays and slow billing processing. The department also misses key infrastructure targets under its network development program. It completes 13.18 kilometers of national roads against a target of 849.71 kilometers, while bridge construction reaches 113.31 lineal meters versus a target of 23,489.08 lineal meters.Financial exposure and operational impact
CoA also flags 50 multi-phase civil works contracts worth P4.62 billion whose project phases remain partially operational, idle, unusable or suspended. The audit finds P4.09 billion in advances to contractors and consultants remain unrecovered from completed, terminated, rescinded or abandoned projects, as well as projects awaiting termination.Inspections identify technical defects in 872 projects worth P4.33 billion, while 300 projects worth P17.34 billion show visible structural defects or discrepancies. For the rehabilitation of Marawi City and surrounding areas, the department disburses only P300,000 out of P1.97 billion obligated, equivalent to 0.02%, despite obligating 89.96% of the P2.19 billion allocated for the program.
State auditors issue a qualified opinion on the agency's 2025 financial statements after identifying P17.28 billion in uncorrected misstatements. The agency also carries P67.93 billion in audit suspensions, P50.15 billion in audit disallowances and P2.83 million in audit charges, bringing total unsettled audit findings to about P118.09 billion.
DPWH says it will implement CoA recommendations, including improving project preparation and monitoring, accelerating billing and strengthening the settlement of audit findings.
In our earlier article on planned Philippine sovereign bond reforms and prospective index inclusion, we explained how these changes could widen the investor base and improve liquidity for peso government securities. We also noted that the bigger payoff depends on fiscal credibility and, crucially, whether any borrowing advantages translate into well-chosen, efficiently executed public spending—especially infrastructure—rather than delayed, overpriced, or poorly managed projects.