KJTS Group Bhd has secured a RM48 million subcontract for mechanical works at a hyperscale data centre in Port Dickson. The contract increases the group's exposure to the data centre segment, with the project scheduled for completion in two phases by January 2028.

Highlights

  • KJ Technical Service Sdn Bhd has secured a RM48 million mechanical subcontract for a hyperscale data centre in Port Dickson from Gamuda Engineering Sdn Bhd.
  • The contract covers engineering, procurement, fabrication, installation and servicing of mechanical systems, and is scheduled for completion in two phases on 22 Oct 2027 and 21 Jan 2028.
  • KJTS shares closed 0.51% lower at 98 sen on Thursday, giving the group a market capitalisation of RM676.9 million.

This article was translated from the original. Read the original version by our correspondent here.

Contract details and scope of work

As reported by The Edge Malaysia, citing a filing with Bursa Malaysia, KJTS's wholly owned subsidiary, KJ Technical Service Sdn Bhd, entered into a subcontract agreement with Gamuda Engineering Sdn Bhd for a hyperscale data centre project being developed for a U.S.-headquartered multinational technology company.

Under the contract, KJTS will carry out the mechanical package, which includes supplying materials, plant and labour for engineering, procurement, fabrication, delivery, installation, supervision, testing and commissioning, as well as the maintenance and servicing of mechanical systems.

The project is scheduled for completion in two phases, with Phase 1 targeted for completion on 22 Oct 2027 and Phase 2 on 21 Jan 2028.

Implications for KJTS and the market

The subcontract award adds to KJTS's order book in the engineering support and building segments, particularly in digital infrastructure, which continues to attract new construction activity in Malaysia. Involvement in a data centre project could also strengthen the group's position in high-value mechanical works, which typically require technical expertise and phased execution.

KJTS shares closed half a sen, or 0.51%, lower at 98 sen on Thursday, giving the group a market capitalisation of RM676.9 million.

Previously, we highlighted how U.S. AI chip restrictions could expand data centre contract opportunities for Malaysian contractors.