Philippines DoE expects Semirara to meet coal mine obligations before 2027 contract award

Philippines DoE expects Semirara to meet coal mine obligations before 2027 contract award
Semirara faces 2027 deadline

As the Philippine government moves to award new coal operating contracts, Semirara Mining and Power Corp. remains bound to complete its commitments at the country’s largest coal mine. The company’s current operating contract for the Semirara mine in Antique expires in July 2027, while officials continue to review industry feedback on the bidding rules.

Highlights

  • Department of Energy requires Semirara Mining and Power Corp. to fulfill all obligations under its coal contract before July 2027 expiration regardless of new bids.
  • DoE plans to award new coal operating contracts, covering areas with 207 million metric tons of reserves including Semirara, to successful bidders by January 13, 2027.
  • Semirara raised concerns about mandatory asset inventory disclosure and ranking bids solely on financial offers, prompting DoE to seek more stakeholder feedback on guidelines.

Coal bidding process and contract obligations

As reported by BusinessWorld Online, the Department of Energy says Semirara Mining and Power Corp. must fulfill all deliverables under its existing coal operating contract regardless of whether it joins the bidding for a new agreement. Energy Secretary Sharon S. Garin told reporters last week that the developer remains obligated to complete the terms of the contract and said she does not expect the company to walk away from the project because of that responsibility.

SMPC has operated the Semirara coal mine in Antique for nearly five decades and is approaching the July 2027 expiry of its current contract. The department is targeting the signing of coal operating contracts with winning bidders by Jan. 13, 2027, ahead of that expiration.

Industry concerns and transparency requirements

SMPC has raised concerns over parts of the government’s coal bidding rules, including requirements to disclose asset inventories, turn over certain assets, and use financial offers as the sole basis for ranking qualified bidders. The DoE recently relaunched its coal bidding round, offering three predetermined areas with combined estimated coal reserves of 207 million metric tons, including the Semirara mine, the company’s flagship asset and the country’s largest coal-producing operation.

Garin says the inventory disclosure requirement is meant to give prospective bidders enough information about the mining areas, including available assets, potential and resource base. She also says the department is seeking additional feedback from stakeholders to address concerns and further refine the bidding guidelines.

Earlier, we discussed China investment pledges tied to Philippine manufacturing and clean energy projects highlighted by President Marcos.

This material may contain third-party opinions, none of the data and information on this webpage constitutes investment advice according to our Disclaimer. While we adhere to strict Editorial Integrity, this post may contain references to products from our partners.