Binastra ends RM160 million construction contract in Selangor after client revises project plans

Binastra ends RM160 million construction contract in Selangor after client revises project plans
Binastra ends Selangor contract

The mutual termination of the contract removes the remaining work on the project from Binastra’s order book, with no material impact expected on the group’s revenue, net assets or gearing. The contract in Damansara Perdana originally covered demolition and main construction works for a development comprising 560 office units, with completion scheduled for July 30, 2026.

Highlights

  • Binastra Corp Bhd and Dynamicz Sdn Bhd mutually terminated the RM160 million construction contract after Dynamicz revised its project plans.
  • Binastra Builders issued progress billings of RM23.82 million, and neither party can claim certain damages following the contract termination.
  • Binastra said the contract cancellation was not expected to have a material impact on revenue or net assets, while its shares fell 2.44% to RM2.40.

This article was translated from the original. Read the original version by our correspondent here.

Contract termination and settlement details

As reported by The Edge Malaysia, citing a filing with Bursa Malaysia, Binastra Corp Bhd and Dynamicz Sdn Bhd mutually agreed on Monday to terminate the RM160 million construction contract to accommodate Dynamicz’s revised project implementation plans and procurement strategy.

The company said its wholly owned subsidiary, Binastra Builders Sdn Bhd, had issued progress billings totalling RM23.82 million to Dynamicz as of the termination date. Binastra stressed that the termination did not constitute an admission of liability or default by either party.

The company also said neither party was entitled to impose or claim certain damages arising solely from, or in connection with, the mutual termination of the contract. Binastra Builders was also required to cease work immediately following the termination and fulfil its obligations under the termination letter, while Dynamicz would arrange an assessment of the work completed as of that date.

The final assessment, settlement of any outstanding payments and release of retention monies remain subject to agreement on the final account.

Impact on order book and share performance

Binastra said the cancellation was not expected to have a material impact on its revenue, net assets or gearing, apart from removing the remaining work attributable to the contract from its order book.

Awarded on August 2, 2024, the contract covered demolition and main building works for a development comprising 560 office units across four floors, one facilities floor, an underground service area, as well as lifts and lift lobbies in Damansara Perdana, Selangor. The project was originally scheduled for completion by July 30, 2026.

Binastra shares closed six sen, or 2.44%, lower at RM2.40 on Monday, giving the group a market capitalisation of RM2.63 billion. The stock has risen more than 11% year to date.