Haily Group wins RM42.05 million subcontract for Johor shop-office development
Haily Group Bhd has secured a subcontract worth RM42.05 million to build 56 semi-detached shop-office units in Bandar Wawari, Iskandar Puteri, Johor Bahru. The project strengthens the Johor-based construction company's order book, with work scheduled to start on 1 Dec 2026 and be completed on 31 May 2028.
Highlights
- Haily Construction Sdn Bhd has secured a RM42.05 million subcontract from PGBG Construction for a shop-office development in Johor for Paragon Globe Properties.
- The subcontract covers the construction of 48 three-storey units, eight four-storey units, three TNB substations and a pump house, with the entire project scheduled for completion on 31 May 2028.
- This is Haily's second major contract in 2024, following the RM48.21 million project at Taman Impian Emas; its shares last closed at 16 sen, giving it a market capitalisation of RM65.57 million.
This article was translated from the original. Read the original version by our correspondent here.
Contract details and implementation schedule
According to The Edge Malaysia, its wholly owned subsidiary, Haily Construction Sdn Bhd, received a letter of award from PGBG Construction Sdn Bhd, the main contractor for the development being undertaken for Paragon Globe Properties Sdn Bhd, a unit of Paragon Globe Bhd.The subcontract covers the construction of 48 three-storey semi-detached shop-office units and eight four-storey units, as well as three Tenaga Nasional Bhd substations and a pump house.
The electrical substations are scheduled for handover on 31 May 2027, followed by two show units on 31 July 2027. Construction of the entire project is scheduled to begin on 1 Dec 2026 and be completed on 31 May 2028.
Implications for Haily's operations in Johor
This is the second major contract announced by Haily this year, following the company's award of work worth RM48.21 million in February to build 111 two-storey terrace houses in Taman Impian Emas, Skudai, Johor.Haily is primarily involved in the construction of residential and non-residential buildings, with operations focused in Johor. Haily shares were not traded on Monday and last closed at 16 sen, giving the company a market capitalisation of RM65.57 million.
Previously, we outlined the key factors behind the quarterly results roundup and new contracts of listed companies in our Malaysia market developments.