MRT Corp expands its RM75 billion development portfolio beyond rail
MRT Corp plans to deliver a development portfolio worth RM75 billion over the next eight years, covering MRT3, the Penang Mutiara Line, the RTS Link, transit-oriented developments and transport hubs. The plan marks an expansion of the role of the company owned by the Minister of Finance (Incorporated), as it also seeks more partnerships with developers and targets the opening of the RTS Link in February 2027, subject to safety certification and regulatory approval.
Highlights
- MRT Corp is now responsible for overseeing a RM75 billion portfolio over eight years, tripling from RM20 billion in 2020.
- Construction costs for the flagship MRT3 Circle Line project are estimated at between RM31 billion and RM32 billion, with the total cost nearing RM40 billion, including RM6.5 billion for land acquisition.
- MRT Corp is expanding private-sector partnerships through projects such as The Linque with IJM Corp, worth RM600 million, and the RM2.6 billion Bukit Chagar integrated development with Sunway, as well as new transport hubs under MRT3.
This article was translated from the original. Read the original version by our correspondent here.
Project pipeline and eight-year development strategy
As reported by The Edge Malaysia, MRT Corp chief executive officer Datuk Mohd Zarif Hashim said the agency is now responsible for delivering a portfolio worth RM75 billion over the next eight years, up from RM20 billion when he took over in 2020.The largest part of the development pipeline is focused on the MRT3 Circle Line, a planned 51km urban route designed as a key missing link in the Klang Valley transit network. Mohd Zarif said he wanted to keep construction costs between RM31 billion and RM32 billion, before accounting for any potential knock-on effects from the West Asia conflict, while land acquisition costs are estimated at around RM6.5 billion and the total cost is close to RM40 billion.
To contain costs, MRT3 is planned as an elevated line using a hybrid system combining LRT and MRT, rather than a fully fledged MRT system. The portfolio also includes the Mutiara Line in Penang, refurbishment work on MRT Kajang Line trains, as well as several transit-oriented development projects and transport hubs.
MRT Corp is also expanding its partnerships with private developers. In addition to The Linque project with IJM Corp Bhd, which has a gross development value of RM600 million at Cochrane station, and the RM2.6 billion Bukit Chagar integrated development with Sunway's property arm, the company is exploring transport hubs in Kota Madani Emas, Salak South, Segambut, Pandan and Titiwangsa as part of the MRT3 development.
We recently reported on the CCUS Roadmap 2050, which projects RM160-170 billion in investment through 27 carbon industry initiatives.