Texas data centre permits resume ahead of expected regulatory shift
Texas is reopening approvals for data centre-related projects as developers race to secure permits before a new political balance takes hold in Austin. The move comes weeks before the state legislature convenes in January under incoming Democratic governor Gina Hinojosa, who campaigned on tighter limits for new facilities.
Highlights
- Texas Commission on Environmental Quality has resumed all data centre project permits, granting air pollution permits for SpaceX's $24bn Boca Chica project, CloudBurst, and Atlas Energy Solutions.
- Ercot faces 474GW of grid connection requests but only qualifies 66.4GW as 'base load', driving delays with formal interconnection studies not set to begin until April 2027.
- Developers, facing grid and regulatory constraints, are increasing behind-the-metre power buildouts in Texas, which accounts for about 45GW of the 90GW U.S. pipeline, while competitor states actively court future projects.
Permit restart accelerates late-stage project approvals
As reported by Financial Times, the Texas Commission on Environmental Quality last week resumes "the issuance of all permits related to data centre projects" after a temporary freeze that many in the sector expected to be short-lived.TCEQ grants three air pollution permits covering SpaceX's $24bn Boca Chica gas-fired power plant and supercomputing facility outside Brownsville, CloudBurst's power plant near San Marcos and Atlas Energy Solutions' facility north-east of Abilene.
The agency resumes issuing permits after receiving a directive from outgoing Republican governor Greg Abbott's office. That directive says the Electric Reliability Council of Texas, or Ercot, has finished gathering information on how data centres affect local communities.
Developers are now pushing to win approvals in the final weeks before the Texas Legislature meets in January. Hinojosa says she will establish a moratorium on new development, end tax breaks for the industry and give local communities a greater say over new construction.
Abbott had already begun to toughen his stance even before the midterm vote, despite previously backing the sector's expansion. His recommendations include requiring data centres to pay their own way, bring their own water and protect the Texas grid.
Grid constraints and policy uncertainty reshape investment plans
The state's data centre boom is already slowing as Ercot processes a large pipeline of connection requests. In August, Ercot is considering more than 474 gigawatts of requests to connect to the grid, but only 204 projects representing 66.4GW meet the qualifications to be conditionally included as "base load" in a September update.Another 158 projects totalling 127.9GW qualify as "studied load", meaning they may receive different allocations and face longer waits for grid access. According to a lawyer familiar with the Ercot process, the interconnection study is only expected to start in April 2027, with no completion date set.
That delay is pushing more developers to build their own power centres, according to analysis by Cleanview, which tracks data centre development. Of 59 U.S. data centres with about 90GW of planned behind-the-metre power capacity, almost half of that capacity is in Texas, where groups benefit from Permian Basin gas supply, extensive pipelines and a comparatively light regulatory environment.
Suppliers are also adapting to the shift. Houston-based ERock, whose Texas data centre clients include Meta, Anthropic and Microsoft, says its natural gas generators can add 1.2GW in 12 months at a cost of $20mn or less, while the company expands its Houston factory to serve a $1.7bn contracted backlog.
Investors and executives say the underlying spending from hyperscalers is still expected to go ahead, but some of it may move out of Texas if scrutiny rises further. John Carrington, ERock's chief executive, says states including Arkansas, Oklahoma and West Virginia are actively courting projects, while Cohen & Steers portfolio manager Tyler Rosenlicht describes the post-midterm environment as a meaningful speed bump rather than a collapse in demand.