Canada refers Whitehorse power centres project to Major Projects Office
Rising winter electricity demand in Yukon is increasing pressure on an isolated grid that cannot draw backup power from neighbouring jurisdictions. The Whitehorse Power Centres project is intended to add new thermal generation capacity, with an initial 15 megawatts targeted by 2028 and later phases potentially reaching 150 megawatts.
Highlights
- Whitehorse Power Centres project, referred to the Major Projects Office, targets 15MW generation by 2028 with total capacity up to 150MW in later phases.
- Design and permitting for the first two centres in Whitehorse have been submitted, with ongoing planning to refine fuel use, timing, and site selection based on demand.
- MPO and Yukon will assess grid upgrades, partnership opportunities with Yukon First Nations, and expanded project scope to boost resilience, reduce outages, and drive regional economic growth.
Project referral and planned capacity buildout
As reported by Government of Canada, citing the Government of Canada, the Whitehorse Power Centres project has been referred to the Major Projects Office as part of federal efforts to strengthen energy security and reliability in the North. Ottawa says the development is meant to support population growth, improve public safety and help ensure sufficient electricity supply for homes, services, businesses and expanding industrial demand.The project proposes at least two thermal power generation centres to help ease strain on Yukon’s electricity system during the coldest and darkest periods of the year. The first phase is expected to provide 15MW of electricity by 2028, while later phases could expand total capacity to as much as 150MW.
Design, planning and permitting work for the first two proposed sites in Whitehorse has been submitted to the Yukon Environmental and Socio-economic Assessment Board. Further planning is set to refine the project’s design, timing, scope, fuel use and location as officials assess future industrial and residential requirements.
Grid resilience and Yukon economic implications
MPO is also set to support the Government of Yukon in reviewing additional grid upgrades needed to accommodate higher generation and transmission capacity. That work includes assessing residential and industrial demand, possible investment opportunities for Yukon First Nations and the private sector, along with decisions on suitable fuel types and locations.The proposed power centres are within the Traditional Territories of the Kwanlin Dün First Nation and Ta’an Kwäch’än Council, and the project scope could extend into other Yukon First Nation Traditional Territories as planning advances. Federal officials say the combined generation and grid upgrades are intended to lower outage risks, speed restoration when disruptions occur and support longer-term economic development in the territory.
The federal government links the referral to its broader electrification strategy, which calls for partnership with territorial and Indigenous governments to secure northern electricity systems. MPO, created to accelerate projects considered nationally significant, is designed to work with project proponents, provinces, territories, Indigenous peoples and other stakeholders to move developments forward.
As we previously wrote, Ottawa backed a $168 million Indigenous loan guarantee for a Coastal GasLink stake acquisition.