Google datacentre project in Belgium faces construction halt over permit dispute
Belgian authorities are ordering Google to stop work on a large datacentre project in Wallonia as a dispute over changes to its planning approval remains unresolved. The case adds to pressure on big technology groups expanding AI-related infrastructure in Europe, where water use and energy demand are drawing closer scrutiny.
Highlights
- Wallonia officials order Google to halt nearly completed construction at the Aiseau-Presles datacentre due to unapproved permit modifications, affecting about 300 workers.
- Regional authorities allege illegal construction of a 3-hectare datacentre after a permit to merge two planned facilities and use 600m3 water/hour from the Sambre River was revoked in August over drought concerns.
- Google appeals the revoked permit to Belgium's council of state with a decision expected 7 January, while environmental scrutiny over datacentre water and power usage intensifies amid AI-driven capacity demand.
Wallonia permit dispute halts project
As reported by The Guardian, citing Agence France-Presse, Wallonia officials have ordered Google to halt construction at the Aiseau-Presles site after determining that requested changes to the original planning permission were not approved. Raphaël Stokis, a regional official, says inspectors found the building was nearly complete, with structural work finished, despite the permit having been refused.Stokis says about 300 workers receive a verbal order to stop work, which is later confirmed in writing to Google. The company says in a statement that it is "committed to maintaining an open and collaborative dialogue" with regional authorities.
Regional government spokesperson Nicolas Yernaux tells AFP that a report is being sent to public prosecutors alleging a major offence tied to the illegal construction of a 3-hectare building. The site, about 15km west of Charleroi on a former coalmine, is one of three datacentres originally planned by Google in a 50-hectare business park.
Water use concerns intensify regional scrutiny
Google's 2025 application seeks to merge two planned facilities into one larger datacentre and switch from air cooling to liquid cooling, drawing 600m3 of water an hour from the nearby Sambre River. Local authorities initially approve the amendment in April, but protests from residents and campaign groups lead Wallonia infrastructure minister François Desquesnes to revoke the modified permit in August over drought concerns.Greenpeace says earlier this week that drone footage shows construction continuing despite the revoked permit, and the group files an emergency appeal with local planning authorities. Google has appealed the minister's decision to Belgium's council of state, with a ruling expected on 7 January.
The dispute highlights a broader tension around datacentre expansion in Europe as technology companies build capacity for the AI boom. Environmental critics argue that large facilities can intensify pressure on regional water resources and electricity systems, especially in areas already concerned about climate and drought risks.
The latest update follows our earlier article on Gazprom power conversion to meet electricity demand from Russian data centres.