EBRD and EU fund Jordan wastewater plant upgrade

EBRD and EU fund Jordan wastewater plant upgrade
Jordan plant upgrade funded

Jordan is securing new funding to expand wastewater treatment capacity in its north as pressure on freshwater supplies continues. The financing supports the rehabilitation and expansion of the Shallala plant, with the upgraded facility set to serve up to 242,000 people through 2050.

Highlights

  • EBRD and EU signed a financing package including a sovereign loan of up to U.S. $55 million and an EU grant of 11.4 million euros to upgrade the Shallala wastewater treatment plant.
  • Upgraded plant to treat 11 million cubic metres of wastewater yearly, meeting demand for up to 242,000 people through 2050 and preserving freshwater resources in northern Jordan.
  • Project includes biogas recovery targeting 4,000 MWh renewable energy per year and expects to cut carbon dioxide emissions by around 2,000 tonnes annually.

Financing package and project scope

As reported by European Bank for Reconstruction and Development, the new package consists of an EBRD sovereign loan of up to U.S. $55 million, or 48.9 million euros, to the Water Authority of Jordan, alongside an EU investment grant of up to 11.4 million euros through the Neighbourhood Investment Platform. The financing agreement is signed at the Jordan-EU Investment Conference.

The investment finances a new treatment line, rehabilitation of existing facilities, improvements to sludge management and the restoration of compliance with national wastewater discharge and reuse standards. Construction is phased to maintain uninterrupted wastewater services during implementation.

Once completed, the upgraded Shallala wastewater treatment plant is set to treat about 11 million cubic metres of wastewater each year for agricultural reuse. That is intended to preserve scarce freshwater resources for municipal use while improving environmental conditions and lowering public health risks in northern Jordan.

Water, energy and regional impact

The upgraded facility is expected to raise treatment capacity to 30,500 cubic metres per day, meeting wastewater treatment demand for up to 242,000 people through 2050. The project also includes recommissioning the plant's biogas recovery facility, which is projected to generate about 4,000 MWh of renewable energy annually.

Those changes are expected to improve energy efficiency and cut annual carbon dioxide emissions by around 2,000 tonnes. The Water Authority of Jordan also receives a technical cooperation package covering project implementation support and a new internship programme with two Jordanian universities, financed by Canada and Spain through the High-Impact Partnership on Climate Action.

In a previous article, we explained how the EBRD’s Jordan visit included talks on investment priorities and the Aqaba-Amman desalination project.

This material may contain third-party opinions, none of the data and information on this webpage constitutes investment advice according to our Disclaimer. While we adhere to strict Editorial Integrity, this post may contain references to products from our partners.