Pakistan central bank revises builder financing rules to support housing supply
Pakistan's central bank has updated financing guidelines for builders, developers and REITs to expand the supply of mortgageable housing units and strengthen the country's housing finance system. The revised framework sets stricter eligibility, valuation and monitoring requirements for banks and development finance institutions financing property projects.
Highlights
- State Bank of Pakistan revised builder and developer financing guidelines, requiring banks and DFIs to set up specialized units and tighten risk management in line with international standards.
- New rules mandate project eligibility through valid licenses or contracts, proof of unencumbered land ownership, and a track record of completed developments for private REITs, builders, and developers.
- Financing requires graded valuation protocols (up to Rs50 million: in-house, Rs50–500 million: one external, above Rs500 million: two externals), independent engineering reviews, and enhanced monitoring, insurance, and audit regimes for project accounts.
Revised framework for developer financing
As reported by Business Recorder, the State Bank of Pakistan has revised the guidelines for builders and developers financing to facilitate lending by banks and development finance institutions, while keeping risk management aligned with prudential regulations for corporate and commercial banking and international best practices.Under the updated rules, banks and DFIs are asked to establish specialized units to expand their financing portfolios for builders and developers while ensuring compliance with the new framework. Eligible REITs, builders, developers or project teams must hold a valid license from the relevant building control authority, where applicable, or have an approved contract or agreement with the competent public sector authority or institution.
Private REITs, builders and developers must also show a strong record of successfully completed projects, supported by a list of recently completed developments. They must have clear and unencumbered title to the land for the project, with no charges, liens or other encumbrances, and the land value is to be recognized as equity contributed by the builder or sponsors.
Risk controls and housing finance impact
A financed project must be capable of generating sufficient cash flow to repay its debt, and banks or DFIs are required to have the technical feasibility report independently reviewed by a reputable engineering firm registered with the relevant authority, such as the Pakistan Engineering Council.The central bank also requires lenders to obtain plot and project valuations from valuers approved by the Pakistan Banks Association, depending on the financing size. For financing of up to Rs50 million, a desktop valuation by the bank or DFI is sufficient. Financing above Rs50 million and up to Rs500 million requires at least one approved external valuation, while financing above Rs500 million requires at least two approved valuers.
Banks and DFIs are further directed to set up regular monitoring mechanisms during the construction phase to ensure proper use of funds. The framework also calls for scrutiny or audit of project accounts, escrow accounts and any other accounts needed for project operations, while requiring comprehensive insurance or Takaful coverage, including Contractor's All Risk Insurance or an equivalent policy.