Heathrow seeks higher passenger charges to fund third runway planning costs
Heathrow is seeking regulatory approval to recover more than £300mn of third runway planning costs through passenger charges over the next 20 years. The move comes as the airport and a rival backer prepare formal planning applications by the end of next year, adding fresh scrutiny to the cost of expanding one of the world's most expensive airport hubs.
Highlights
- Heathrow plans to spend up to £304mn and Heathrow West £35mn on third runway planning in H1 2027, subject to CAA consultation on cost recovery via passenger fares.
- If both applications' costs are reimbursed, average ticket price at Heathrow would rise by about 70p per passenger.
- Heathrow has already spent £320mn over two years on planning and warns investors may reconsider the £33bn scheme without political backing from Prime Minister Andy Burnham by year-end.
Regulator reviews runway cost recovery
As reported by Financial Times, citing the Civil Aviation Authority, Heathrow plans to spend up to £304mn in the first half of 2027 on its planning application for a third runway, while Heathrow West, backed by hotelier Surinder Arora, intends to spend £35mn over the same period.The regulator launched a consultation on Wednesday on whether all or part of those costs should be recouped through ticket prices. If the combined spending of both applications is reimbursed and passed on to passengers, the average fare from Heathrow would rise by about 70p.
Tim Johnson, the CAA's consumer director, says the regulator is trying to strike a balance that allows credible expansion proposals to come forward, but only where there is clear evidence that costs are efficient, appropriately justified and deliver value.
Expansion debate sharpens around cost and politics
Heathrow has spent about £320mn over the past two years preparing its application, and the latest planned outlay would almost double the amount it has committed so far to paperwork linked to the project. The airport has said it will not begin formal work on planning approval unless it receives political backing from Prime Minister Andy Burnham before the new year.The airport's chief executive has warned that international investors could reassess the viability of the scheme without a timely go-ahead. Heathrow's £33bn proposal, led by Heathrow Airport Holdings, includes a 3,500-metre runway across the M25 and a new terminal facility.
Heathrow West is proposing a shorter runway that could be extended later if needed, although it would still cause major disruption to roads around the airport. British Airways and Virgin Atlantic, Heathrow's two largest airline customers, have said they prefer the shorter option as a way to keep project costs down.
As we previously wrote, UK regulators consulted on a coordinated CTP fee recovery model for oversight of critical third parties.