Agratas battery plant faces renewed construction risk at UK gigafactory
Delays are deepening at a battery factory project seen as central to the UK automotive supply chain and to Jaguar Land Rover's future domestic EV sourcing. The setback raises fresh uncertainty over whether the Somerset site can meet its latest January 2028 target after a second lead contractor exits within five months.
Highlights
- TSL is exiting Agratas' £5.2 billion Bridgwater gigafactory within two to three months after failing to agree on timetable and cost terms.
- Contractor turnover, including June's removal of Sir Robert McAlpine and no replacement for TSL, threatens Agratas' ability to meet its revised January 2028 production target.
- Jaguar Land Rover secured battery supply from other sources, ensuring no immediate production disruption, but first electric models will not use British-made batteries.
Contractor dispute adds pressure to project timeline
As first reported by The Guardian, construction specialist TSL is leaving Agratas' £5.2 billion gigafactory project in Bridgwater, Somerset, after the two sides failed to agree terms, according to three sources cited in the report. The battery plant is being developed to supply Jaguar Land Rover, with both companies owned by Tata Group, and has already received a £380 million UK government support pledge because of its importance to Britain's car industry.The reported breakdown with TSL stems from disagreements over the project's timetable and cost. TSL, formally known as Tonroe Group, is expected to leave the site within two or three months, with no replacement main build contractor yet in place, although NG Bailey is seen as one possible option to take over a wider role.
The dispute follows an earlier rupture with Sir Robert McAlpine, which Agratas removed from the project in June. Tata announced the factory in 2023 with production initially targeted for 2026, later moving that date to 2027, and the latest contractor change is likely to intensify doubts over Agratas' current January 2028 goal, even though the company says it remains on track to meet customer requirements.
Battery supply and industry implications for the UK
The Somerset plant is viewed as strategically important because EV battery production remains heavily concentrated in China, South Korea and Japan, while UK governments have backed efforts to build a domestic battery supply chain. Not all of the subsidy pledged for the project has yet been paid, and further disruption could sharpen concerns over execution risk in a sector already under pressure from slower EV demand growth and shifting policy timelines.Jaguar Land Rover is understood to have secured batteries from other suppliers, so its rollout of new electric Land Rovers and Jaguars is not expected to be disrupted. However, the first wave of those vehicles will not use British-made batteries, although JLR could still avoid EU tariffs under rules of origin if it uses batteries produced in Europe.
Agratas has nevertheless made progress at the site, where the main shell is largely complete and National Grid has begun work on the electricity substation needed for battery production. The company is also developing a site in Sanand in western India, while internal strain has reportedly increased after some staff were asked to relocate from Coventry to Somerset, adding to senior departures in recent months.
In a previous article, we explained Binastra contract termination after revised project plans led to ending a RM160 million Selangor deal.