Malaysia delays delivery of second LCS following first ship's delay

Malaysia delays delivery of second LCS following first ship's delay
Malaysia’s second LCS delayed

Malaysia’s Littoral Combat Ship program is facing schedule adjustments after delivery of the first ship was postponed to April 2027. The delay has also affected the second ship, KD Raja Muda Nala, although the government still expects it to be delivered next year.

Highlights

  • Malaysia’s Ministry of Defence postponed delivery of the second Littoral Combat Ship and will set a new schedule following the first LCS’s delay until April 2027.
  • Malaysia selected Roketsan’s ATMACA anti-ship missile from Türkiye to replace Norway’s Naval Strike Missile for the LCS program.
  • The Malaysian government is taking legal action following Norway’s unilateral revocation of the missile export licence to protect the country’s financial interests.

This article was translated from the original. Read the original version by our correspondent here.

Warship delivery schedule revised

The Edge Malaysia reported that Deputy Defence Minister Adly Zahari said a new delivery date would be set for the second Littoral Combat Ship following the delay to the first ship. He told the House of Representatives that postponing delivery of the first LCS until April had a direct impact on the LCS2 schedule.

According to Adly, the next three ships remain on their respective original schedules. In January, Defence Minister Datuk Seri Mohamed Khaled Nordin told the House of Representatives that the first LCS was scheduled for delivery in December 2026, followed by LCS2 in August 2027, LCS3 in December 2027, LCS4 in August 2028 and LCS5 in April 2029.

However, delivery of the first ship was later postponed to April 2027. Lumut Naval Shipyard Sdn Bhd, the shipbuilder, previously attributed the delay to the technical and regulatory complexities and contractual issues surrounding the overall program.

Missile choice and legal action

In a separate development, Adly also explained the government’s decision to select Roketsan’s ATMACA anti-ship missile from Türkiye to replace Kongsberg’s Naval Strike Missile, or NSM, from Norway for the LCS program. He said Roketsan was already involved in developing missiles for the Littoral Mission Ship program, which is currently on schedule, and that the ministry had discussed coordinating missile development for both programs.

According to him, Roketsan said the missile could be developed within six months. However, the government did not want the proposed development to disrupt the existing LMS program, while ensuring that the LCS program met the navy’s capability requirements.

Adly also said the government had not held talks with Norway following the country’s unilateral decision to revoke the export licence for the surface-to-surface missile system planned for the ships. Malaysia instead decided to proceed with legal action, although he acknowledged that the process would take time, to protect the country’s financial interests and defend its integrity as a sovereign nation.

As we noted earlier, we reported on MHB’s profit growth, supported by its marine and heavy engineering segments.