Bangladesh secures World Bank financing for Chattogram water supply project
Bangladesh is adding fresh multilateral funding to keep a major urban water project in Chattogram on track through the end of the decade. The additional $140 million follows an earlier reallocation from the project’s original budget and is intended to help restore delivery targets for safe and climate-resilient water services.
Highlights
- Bangladesh secured a new $140 million financing agreement with the World Bank's IDA Scale-up Window for the Chattogram Water Supply Improvement Project, signed 4 November.
- The loan features a 12-year repayment term with a six-year grace period and zero interest, service charges, or commitment fees on withdrawn amounts.
- Additional funds address shortfalls after $140 million of the initial $240 million project allocation was redirected, aiming to expand water access and improve Chattogram Wasa's operational efficiency through 2030.
Financing terms and project timeline
As reported by The Business Standard, citing the World Bank, Bangladesh and the International Development Association signed the additional financing agreement on 4 November for the Chattogram Water Supply Improvement Project.Economic Relations Division Secretary Shahriar Kader Siddiky and World Bank Division Director for Bangladesh and Bhutan Jean Pesme signed the agreement. The project began in 2025 and is scheduled to continue until December 2030, with implementation led by Chattogram Water Supply and Sewerage Authority under the Local Government Division.
The new financing totals $140 million, equivalent to 102.30 million special drawing rights, and comes from the IDA Scale-up Window, Shorter Maturity Loan facility. The loan carries a 12-year repayment term, including a six-year grace period, with no interest, service charges or commitment fees on the withdrawn amount.
Operational goals for Chattogram Wasa
The added funding is intended to help complete project targets after $140 million from the original $240 million allocation was redirected to the Contingency Emergency Response Component.The project is designed to expand access to safe, reliable and climate-resilient water supply in the port city while also improving sanitation services. It also aims to strengthen the financial and operational performance of Chattogram Wasa, linking infrastructure delivery with utility management improvements.
Our earlier article on sovereign borrowing risks in a higher-rate environment explained how prolonged geopolitical shocks and elevated public spending are straining government finances as refinancing costs stay high. We noted that emerging and frontier markets are particularly exposed because interest-service burdens are often heavy relative to limited revenue bases, while persistent inflation pressures can further weaken fiscal headroom and credit outlooks.