Pakistan solar project sponsors seek tariff changes for delayed 50MW plants

Pakistan solar project sponsors seek tariff changes for delayed 50MW plants
Pakistan solar tariff shakeup

Pakistan's power regulator is scrutinising requests from three 50MWp solar project sponsors to revise tariff terms tied to construction timing and financing costs. The petitions could affect how Commercial Operation Date assumptions, Interest During Construction and Return on Equity During Construction are applied to projects originally awarded tariffs in 2020.

Highlights

  • NEPRA questioned sponsors of Medrian Energy Limited, HNDS Energy Limited, and Helios Power Limited over requested changes to Rs5.6988/kWh solar project tariffs set in February 2020.
  • The sponsors seek to shift the 10-month construction timeline from the Financial Close date of February 19, 2021, to the actual Construction Start Date of June 14, 2022.
  • NEPRA is assessing if revising tariff triggers and adjusting for delays would financially impact electricity consumers compared to previous regulatory decisions.

Regulator reviews tariff relief requests

As reported by Business Recorder, the National Electric Power Regulatory Authority, NEPRA, on Tuesday questioned the sponsors of Medrian Energy Limited, HNDS Energy Limited and Helios Power Limited over separate petitions to amend tariff determinations issued on February 21, 2020.

NEPRA had set a levelised tariff of Rs5.6988 per kWh, equivalent to U.S. cents 3.6684 per kWh, for the three projects. During the hearing, authority members Amina Ahmed, Maqsood Anwar Khan and Ghulamullah Shaikh asked the sponsors and the Central Power Purchasing Agency-Guarantee, CPPA-G, to justify the requested changes and explain the potential financial implications for electricity consumers.

The companies say they are seeking relief similar to that granted to certain other power producers. They argue that land acquisition problems and other project-related difficulties prevented construction from starting within the originally envisaged timeframe, forcing them to revise the projects' feasibility studies and schedules.

Construction timing and consumer impact

The petitioners have asked NEPRA to remove the 10-month construction period linked to the Financial Close date of February 19, 2021, and instead allow that period to begin from the Construction Start Date of June 14, 2022, as provided in the Energy Purchase Agreement.

They also contend that tariff implementation, along with adjustments to Interest During Construction and Return on Equity During Construction, should be aligned with the actual start of construction and the underlying project agreements. NEPRA's review now centres on whether the requested revisions are consistent with prior regulatory treatment and whether any relief would shift additional costs onto Pakistan's electricity consumers.

The latest update follows our earlier article on Heathrow passenger charges to recover third-runway planning costs through fares.