Chevron Gorgon vented methane as CCS constraints hit LNG operations in Western Australia
Methane emissions detected above Chevron's Gorgon LNG project are drawing renewed scrutiny to the plant's emissions controls and carbon management systems. Western Australia's environmental regulator says the plumes that triggered a United Nations warning in August were deliberate venting linked to constraints in the facility's carbon capture and storage system.
Highlights
- Western Australia's regulator found the August 29, 2026, methane venting at Chevron's Gorgon facility resulted from CCS system constraints, not unauthorized leaks.
- Satellite data show average methane emissions at Gorgon hit 4.9 tonnes per hour between November 2025 and August 2026, nearly five times the previously reported rate.
- Chevron's Gorgon CCS system underperformed since inception, resulting in over 4 million tonnes of CO2 vented and potential breaches of environmental approvals amid strong LNG market conditions.
Regulator findings on the August emissions event
As reported by ABC News, Western Australia's Department of Water and Environmental Regulation says the 29 August 2026 emissions event at the Gorgon gas project was associated with venting through approved facility infrastructure when constraints affected operation of the carbon capture and storage, or CCS, system.Environment Minister Matthew Swinbourn says the regulator found no evidence that the detected emissions were caused by an uncontrolled leak, upset condition, incident, or unauthorised emissions source. The finding follows a United Nations alert issued in August after large methane plumes were detected above the Barrow Island facility, about 60 kilometres off the West Australian mainland.
Satellite observations recorded on five consecutive occasions between November 2025 and August 2026 estimated average methane emissions of 4.9 tonnes an hour, nearly five times the rate reported at Gorgon over the past two years. Chevron says it has worked constructively with the regulator and remains committed to responsibly managing emissions, including methane.
CCS performance and approval concerns
Claims tabled in the Western Australian parliament by Greens MLC Sophie McNeill include a whistleblower statement alleging Chevron deliberately released methane rather than reduce production, while linking the emissions to the project's troubled CCS system. Chevron's own reporting shows LNG production at Gorgon has regularly exceeded its stated design capacity of 15.6 million tonnes a year, as global LNG prices remain near multi-year highs after attacks on Qatari suppliers and shipping disruptions in the Strait of Hormuz.McNeill says the emissions may breach Gorgon's environmental approvals, which provide for no routine venting or flaring except where normal operations are unavailable. The project is required to sequester 80 percent of the carbon dioxide produced from Gorgon's carbon-rich gas fields, but engineering problems delayed the CCS system for the first three years of gas exports and it has remained below that benchmark since.
The methane plumes appear to originate near the plant's three acid gas removal units, where raw gas is stripped of carbon dioxide and other impurities before the CO2 is sent for underground injection. Chevron says challenges have constrained injection rates and that optimisation projects are under way, while energy researcher Tim Baxter says the latest data points to a cascading series of failures and indicates more than 4 million tonnes of CO2 have been vented since the CCS project began.
We have previously detailed proposals for a transparent carbon market framework in the Philippines, including phased pricing and stronger safeguards.