U.S. data center construction costs climb as AI demand strains land, power and labor
A sharp buildout of artificial intelligence infrastructure in the U.S. is pushing large data center development beyond available powered land and construction labor this year. That imbalance is extending project timelines, raising contractor risk and lifting construction costs far faster than the global average.
Highlights
- U.S. large-scale data center construction costs are projected to rise 13% year over year in 2026, more than double the global rate.
- Power availability is a key constraint, with 56% of global respondents citing it as a major obstacle and utility connections often taking over one year.
- Global data center capex is expected to rise from about $800 billion in 2024 to $1.8 trillion annually by 2050, with the U.S. set to capture nearly half of AI infrastructure investment.
Cost pressures intensify across 2026 projects
As reported by CNBC, citing Turner & Townsend, construction costs for large-scale U.S. data centers rise 13% year over year in 2026, more than twice the global rate and about three times the last 10-year average. The project management company says the increase reflects not only stronger demand, but also the pace at which developers want capacity delivered.The report covers more than 500 live or recently completed projects across 62 global markets and includes a survey of 400 data center industry experts. It says some cost inflation stabilizes this year, but not enough to offset rapid growth in demand and tighter construction schedules.
Paul Barry, North America data center lead for Turner & Townsend, says aggressive schedules are leading contractors and subcontractors to build more risk allowances into pricing. Those allowances include acceleration costs, overtime, labor attraction measures and higher fees for taking on faster-than-normal delivery commitments.
Power delays and labor shortages reshape market outlook
Power availability remains a central constraint for the sector. Turner & Townsend says 56% of respondents globally identify power as a major obstacle to delivery, while just over half say utility connections typically take between one and two years, and almost a third report waits of more than two years.Regional power-related costs also vary widely, with a typical 60-megawatt design costing $15.01 per watt in Silicon Valley versus $10.51 per watt in Dallas. Labor remains another major headwind in the U.S., with just over one quarter of respondents saying contractor capacity is sufficient to manage construction backlogs.
Barry says cost growth is expected to moderate next year, with increases in the 6% to 10% range as major projects already under way have largely priced in risk. Even so, broader spending remains on an upward path, with PwC projecting global data center capital expenditure to rise from about $800 billion this year to $1.8 trillion annually by 2050, while the U.S. is expected to capture nearly half of worldwide investment in AI infrastructure.
Earlier, we discussed Phoenix zoning rules as the city sought tighter control over AI-driven data center growth and resource strains.