U.S. data centre expansion threatens to raise power-sector emissions
Rising electricity demand from large new data centres is increasing the risk that U.S. power-sector emissions climb despite years of corporate clean energy pledges. An analysis of 60 major planned facilities shows their combined annual carbon output could reach 101.5 million tonnes once fully operational under the current U.S. power mix.
Highlights
- The 60 largest planned U.S. data centres by Amazon, Microsoft, Google, and Meta could account for 7 per cent of 2025 U.S. power-sector emissions, equating to 27 coal plants.
- Three-quarters of utilities supplying these data centres are adding new gas-fired capacity, with a third delaying coal-plant retirements and 17 per cent citing direct demand from hyperscale centres.
- Amazon's emissions rose 16 per cent and Microsoft's 25 per cent from 2024 to 2025 due to data centre growth, while overall grid reliance on fossil fuels increases to meet AI-driven demand.
Planned capacity and emissions outlook
As reported by Financial Times, the 60 largest planned data centres being built in the U.S. by Amazon, Microsoft, Google and Meta could together generate annual emissions equal to 27 coal plants or 24 million petrol-powered cars. The estimate is based on the latest snapshot of U.S. power generation and indicates the facilities could account for about 7 per cent of U.S. power-sector emissions in 2025 once fully operational.Jonathan Koomey, an energy researcher focused on efficiency and climate solutions, says the estimate is a reasonable ballpark figure. He says the share is still relatively small in the context of the full power system, but represents a significant increase from what data centre companies had indicated in their emissions-reduction plans five years ago.
The analysis also points to a broader challenge for the electricity system as AI infrastructure expands. Although the U.S. grid has added more clean energy since 2023, utilities serving these projects are also adding fossil-fuel generation because they face a sharp rise in around-the-clock electricity demand.
Utility response and pressure on climate goals
Three-quarters of the utilities serving the 60 projects are planning or building new gas-fired capacity, based on utility filings, S&P data and DC Byte. A third of the utilities that operate coal plants are also delaying retirements, while 17 per cent of operators serving the projects have explicitly told regulators that new gas plants are being built to meet demand from a specific hyperscale data centre.Taylor McNair, deputy director at clean-energy consultancy GridLab, says utilities tend to turn to gas generation when demand spikes because it is the easiest option. He says recent load growth has disrupted momentum in renewable deployment, even as grid operators and utilities increasingly prioritise fuels they view as dependable for continuous supply.
Global Energy Monitor says the U.S. nearly tripled its gas-fired capacity in development in 2025, a pipeline that could expand the existing gas fleet by almost 50 per cent if all plants are built. More than one-third of that capacity is intended to power data centres on site.
At the same time, some technology groups are acknowledging in sustainability reports that emissions are rising with their infrastructure expansion. Amazon says its emissions increased 16 per cent from 2024 to 2025 and that emissions tied to purchased electricity rose 34 per cent, while Microsoft says total emissions increased 25 per cent over the same period, driven mainly by data centre growth. Alphabet says its ambition-based emissions increased 18 per cent because of supply-chain activity linked to rapid business expansion, though it says its 2025 carbon footprint would have been five times larger without other decarbonisation efforts.
All four companies say they plan to match electricity consumption with clean energy investments, often through renewable energy credits. Still, the pace of data centre construction is adding pressure to U.S. decarbonisation efforts as the power system leans on fossil fuels to meet surging AI-related demand.
In our earlier article on emissions from the 60 largest planned U.S. data centres by Amazon, Microsoft, Google and Meta, we highlighted estimates that these projects could account for about 7% of U.S. power-sector emissions in 2025 under the current generation mix. We also noted that many utilities serving these sites are turning to new gas capacity and delaying some coal retirements, creating fresh pressure on corporate climate targets as AI-related electricity demand rises.